The road stretch from the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction is scheduled to reopen to traffic between December 15 and 20, 2026. This development follows the 90% completion of the first phase of a major drainage improvement project under the Greater Accra Resilient and Integrated Development (GARID) initiative. The reopening is strategically timed to alleviate the heavy vehicular congestion that typically characterizes the capital during the Christmas festive season. Project Manager Cephas Ofori confirmed that the structural components of the first phase are nearly finished, marking a significant milestone in the city's infrastructure development. According to Mr. Ofori, the remaining tasks for the contractor include backfilling the excavated sections and restoring the road pavement to ensure safety and smooth transit for motorists. The road was originally closed on September 7 to facilitate these critical drainage interventions, which are designed to improve the area's flood management. Throughout the construction period, project officials noted that effective traffic management plans and the implementation of alternative routes successfully mitigated potential gridlock on this vital transport artery. The project has moved swiftly, with Phase Two already commencing to extend improvements from the Pamprom Crossing toward the First Light area. This continued infrastructure work is part of a broader strategy to bolster Accra’s resilience against seasonal flooding and improve urban mobility. Authorities have urged the public to continue following directional signs and cooperating with traffic wardens as the final restoration works are completed on the Phase One site while work progresses on the subsequent phases.