Dr. Mohammed Amin Adam, the former Finance Minister, has raised alarms over the slow implementation of Ghana’s Big Push infrastructure programme, revealing that the initiative is falling significantly behind schedule. Speaking during a parliamentary debate on the 2027 Budget, Dr. Adam disclosed that as of June 2026, only 13 projects within the framework have reached at least 50% completion. This disclosure highlights a perceived stagnation in the rollout of what was intended to be a major developmental drive.
Providing a further breakdown of the programme's status, the former minister noted that 15 projects are currently situated between the 25% and 50% completion mark. However, his most pointed criticism focused on the lack of transparency surrounding the bulk of the initiative. Dr. Adam asserted that 59% of the projects lacks any formal accountability regarding their status, leaving lawmakers and the public in the dark about whether work has even commenced or if the funds allocated for them have been utilised effectively.
Dr. Adam criticised the government’s oversight of the programme, demanding immediate clarity on implementation strategies and expenditure. He argued that the absence of detailed reporting undermines the integrity of the infrastructure initiative and necessitates a thorough audit of how funds have been disbursed. As the parliamentary debate on the 2027 Budget continues, these revelations are expected to intensify pressure on the administration to provide a comprehensive account of the Big Push projects to ensure value for money and the timely delivery of critical infrastructure.